LEGEND
CRITICAL PATH
FLOAT ACTIVITY
GANTT CHART VIEW
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Pour foundation
3 Days
A
Erect frame
4 Days
B
Roof
4 Days
C
Windows
1 Days
D
FLOAT
Doors
3 Days
E
FLOAT
Electrical
2 Days
F
FLOAT
Rough-in frame
2 Days
G
Door opener
1 Days
H
FLOAT
Paint
2 Days
I
Cleanup
1 Days
J
ACTIVITY TABLE
| ID | Activity Name | Predecessor | Duration | Type |
|---|---|---|---|---|
| A | Pour foundation | - | 3 Days | CRITICAL |
| B | Erect frame | A | 4 Days | CRITICAL |
| C | Roof | B | 4 Days | CRITICAL |
| D | Windows | B | 1 Days | FLOAT |
| E | Doors | B | 3 Days | FLOAT |
| F | Electrical | B | 2 Days | FLOAT |
| G | Rough-in frame | C, D, E, F | 2 Days | CRITICAL |
| H | Door opener | E, F | 1 Days | FLOAT |
| I | Paint | G, H | 2 Days | CRITICAL |
| J | Cleanup | I | 1 Days | CRITICAL |