HOUSE CONSTRUCTION TIMELINE

Project ID: HCT-2025-001

MENU
LEGEND
CRITICAL PATH
FLOAT ACTIVITY

CRITICAL PATH: Sequence of stages determining the minimum time needed for an operation.

FLOAT: Amount of time that a task can be delayed without causing a delay to subsequent tasks or project completion.

GANTT CHART VIEW
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Foundation
2 Days
A
First Floor
5 Days
B
Decking
1 Days
C
Second Floor
5 Days
D
Roof
2 Days
E
Door Installation
1 Days
F
FLOAT
ACTIVITY TABLE
IDActivity NamePredecessorDurationType
AFoundation-2 DaysCRITICAL
BFirst FloorA5 DaysCRITICAL
CDeckingB1 DaysCRITICAL
DSecond FloorC5 DaysCRITICAL
ERoofD2 DaysCRITICAL
FDoor InstallationC1 DaysFLOAT