CRITICAL PATH
FLOAT ACTIVITY
CRITICAL PATH: Sequence of stages determining the minimum time needed for an operation.
FLOAT: Amount of time that a task can be delayed without causing a delay to subsequent tasks or project completion.
GANTT CHART VIEW
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Foundation
2 Days
A
First Floor
5 Days
B
Decking
1 Days
C
Second Floor
5 Days
D
Roof
2 Days
E
Door Installation
1 Days
F
FLOAT
ACTIVITY TABLE
| ID | Activity Name | Predecessor | Duration | Type |
|---|---|---|---|---|
| A | Foundation | - | 2 Days | CRITICAL |
| B | First Floor | A | 5 Days | CRITICAL |
| C | Decking | B | 1 Days | CRITICAL |
| D | Second Floor | C | 5 Days | CRITICAL |
| E | Roof | D | 2 Days | CRITICAL |
| F | Door Installation | C | 1 Days | FLOAT |